What is the In Ground Trampoline Installation Process

Capital’s in-ground trampoline kits are made to be simple to assemble and install. Over of their customers assemble and install their furniture with the help of family and friends. Many customers additionally hire local gardening or landscaping companies, or simply hire some local muscle to help with the hole digging.

It is a frequent fallacy that if a person falls on an in-ground trampoline, they will be less gravely hurt than if they fall on an above-ground trampoline. Even if the jumper is closer to the ground if a safety enclosure is not in place, they can still fall from a great height, possibly six or more feet, and land on hard ground, commonly a retaining wall’s a hard surface. Furthermore, extra space between the trampoline’s ends is often required for optimal ventilation and drainage.

In-ground trampoline installation is being done by the experts and it can take longer and cost more to construct. They must be put in an area that allows for 3-4 feet of digging without hitting any rocks or utilities. They will also have to think about how rain, snow, and even typical gardening will drain out from below the trampoline. Insect infestations and rusting can be caused by stale and stagnant water in the backyard.

Dig a hole a few inches larger in diameter than their trampoline. This will allow folks to fit the trampoline into the hole with a little more room. 25cm of the earth should be dug out uniformly throughout the entire hole. Then, in the middle, dig a bowl-shaped inner hole 2 feet or 60cm smaller in diameter than the trampoline size, to a depth of 90cm for 12ft and 14ft trampolines and 75cm for 8ft and 10ft trampolines. This will create a ledge for the trampoline frame to rest on.

Assemble the frame

  • Assemble the trampoline frame’s top and bottom components, attach the mat and springs, and secure the retaining wall to the frame’s outside.
  • Lift the trampoline into the hole and position it on the ledge, making sure the frame is at the proper height. Then, on the outside of the frame, backfill the gap, compact the dirt, and re-turf.